Client
Translink
Location
Belfast City Centre
Date / Duration
28 weeks
Sector
Civil Engineering
Scope
Concrete framed multi-storey car park in Belfast city centre.
- Completed Hydro blasting to levels 3 & 4 removing and replacing 5000m2 of failed concrete decking
- Installed 240 galvanic anodes and 13,000 hybrid anodes into the concrete decks and columns
- Placed 2000m2 of corrosion inhibitor
- Completed the works placing 5000m2 of elastomeric deck coatings throughout
- Phased with minimal disruption to users