22 railways from Larne to Belfast upgraded

22 railway lines through Belfast – Larne line and Belfast – Derry line rail network.

Client Name:

Translink

Project Details:
This project was similar to the works undertaken in Package l. The works involved managing numerous live sites with day and night working on the Belfast – Larne line and Belfast – Derry line rail network.

Location:
22 railway stations on the Belfast – Larne line and Belfast – Derry line

23 Stations & Halts for NI’s Largest transport company.

total refurb fro 23 railway stations throughout NI, completed by Cleary Contracting Ltd

Details:

Client Name:

Translink

Project Details:
The complete upgrade of passenger services at 23 stations & halts throughout rail network, this involved new surfacing on every platform, the installation of passenger lifts in Lisburn & Botanic Stations.
Internally in Portadown, Lurgan, Lisburn and Botanic Stations new DDA compliant Ticket & Help Desks were constructed with removal of the existing and alterations required to internal offices to accommodate new works, these stations all remained operational for the duration of the works. With both the staff and members of the public alongside the ongoing works, our approach to managing the public and staff were paramount to the works being carried out safely and was essential to the successful completion of the works on-time.

Location:
23 railway stations on the Belfast – Bangor line and Belfast – Border line

Glasgow Subway Upgrade

Cleary Contracts start work in Glasgow with 15mill budget for renovations to Glasgow subway station

Cleary Contracting ltd carried out all DDA enhancements throughout all 14 subway stations. in Glasgow.

The works included new escalators, improved signage and passenger information, public artwork and the creation of new ticket offices and retail space.

It includes DDA enhancements such as hearing loops and tactile maps and paving.

To avoid passenger disruption, most of the works were carried out in short night-time possessions and at weekends by the Cleary Contracting team.