Skip to content

Project

Harland & Wolff Ship Assembly Building

Back to projects

Client

Harland & Wolff Navantia UK

Location

Belfast

Date / Duration

72 weeks

Sector

Industrial

Scope

50,000sqft extension to the existing facility to form a new ship assembly production line

 

  • 800mm CFA concrete piled foundations to 20m depths
  • Steel portal frame with insulated cladding envelope
  • Super flat floors with large recesses formed for production line
  • Extensive concrete yards created for loading lorries
  • 2nr new HV transformers installed
  • Heavily serviced with M&E provisions throughout for ship assembly line