Client
Harland & Wolff Navantia UK
Location
Belfast
Date / Duration
72 weeks
Sector
Industrial
Scope
50,000sqft extension to the existing facility to form a new ship assembly production line
- 800mm CFA concrete piled foundations to 20m depths
- Steel portal frame with insulated cladding envelope
- Super flat floors with large recesses formed for production line
- Extensive concrete yards created for loading lorries
- 2nr new HV transformers installed
- Heavily serviced with M&E provisions throughout for ship assembly line